articles

I-15/French Valley Parkway Project Updates

By Ashley Cunningham, Publisher - Macaroni Kid Temecula-Murrieta-French Valley July 3, 2023

I-15/French Valley Parkway Project (I-15/FVP)

Phase 1 (Red) is done.

Phase 2 (Blue) is under construction. 

I-15/FVP Phase 2 improvements (shown in blue above) will reduce daily northbound traffic congestion by eliminating merging/weaving upon construction of collector/distributor lanes along northbound Interstate-15, separating streams of traffic between Winchester Road and the I-15/215 junction. The major project components include:

•Construction of two Northbound I-15 collector/distributor lanes spanning over two miles along Interstate-15 between Winchester Road and the I-15/215 Junction.

•Construction of a concrete barrier along I-15 to separate freeway traffic from vehicles entering Northbound I-15 from Winchester Road.

•Flyover bridge at the I-15/215 Junction.

•Construction of 10 retaining walls.

•Anticipated construction completion: Winter/Spring '25

Visit the City's I-15/FVP Improvements webpage to stay informed.
//

Ynez Road between Rancho Vista Road and Tierra Vista will be widened to two lanes in each direction, with construction of a new sidewalk along the east side. This project is currently in the design phase, and is anticipated to be completed in 2024.